01What it is
The Costs and profitability tab is only for people with the finance permission. It shows the contracts that were in force or ended in the chosen period: revenue, hours worked, labour cost, fault costs, materials costs, margin and margin as a percentage.
Revenue is the net monthly value of the contract multiplied by 12 and divided by 365, for the contract days within the period. Labour cost is the attendance time at the contract sites multiplied by the hourly rate of the person. Fault costs are the costs entered on faults at those sites in the period. Materials costs are the materials used on tasks at those sites, at the price on the day of use. Margin is revenue minus labour, fault and materials costs.
A site covered by several contracts shares its cost equally between them. Hours of people without a rate do not enter the labour cost. They are shown separately, and a hint above the table asks you to fill in the rates.
You enter rates in the Rates tab: a net hourly rate and the date from which it applies. For each working day the latest rate valid up to that day is used, so the rate history is kept.
- REVENUE
- Monthly value times 12 over 365, for the days in the period.
- LABOUR COST
- Attendance time times the hourly rate of the person.
- FAULT COSTS
- Costs entered on faults at the contract sites.
- MATERIALS COSTS
- Materials used on tasks at the contract sites, at the price on the day of use.
- MARGIN
- Revenue minus labour, faults and materials, also as a percentage.
02Tasks step by step
- STEP 1Open Reports and go to the Rates tab.
- STEP 2For each person enter the net hourly rate and the date from which it applies.
- STEP 3Go to the Costs and profitability tab and set the period.
- STEP 4Check the contract margins and make sure there are no hours without a rate.
03What it connects to
Contracts
The monthly value and sites of a contract come from the Contracts screen.
Go to the topicContractsHistory and costs
You enter fault costs on the fault record.
Go to the topicHistory and costsAttendance and time
Labour cost is calculated from the time recorded in Attendance.
Go to the topicAttendance and time