Cost and profitability

For each contract you see revenue, labour cost, fault costs, materials costs and margin in a chosen period. Labour cost is calculated from attendance time and hourly rates.

IN THE APP
Insight › Reports › Costs and profitability
SCREEN
Insight, Reports
TABS
Costs and profitability, Rates
ACCESS
Finance permission
CONNECTIONS
3 modules

01What it is

The Costs and profitability tab is only for people with the finance permission. It shows the contracts that were in force or ended in the chosen period: revenue, hours worked, labour cost, fault costs, materials costs, margin and margin as a percentage.

Revenue is the net monthly value of the contract multiplied by 12 and divided by 365, for the contract days within the period. Labour cost is the attendance time at the contract sites multiplied by the hourly rate of the person. Fault costs are the costs entered on faults at those sites in the period. Materials costs are the materials used on tasks at those sites, at the price on the day of use. Margin is revenue minus labour, fault and materials costs.

A site covered by several contracts shares its cost equally between them. Hours of people without a rate do not enter the labour cost. They are shown separately, and a hint above the table asks you to fill in the rates.

You enter rates in the Rates tab: a net hourly rate and the date from which it applies. For each working day the latest rate valid up to that day is used, so the rate history is kept.

REVENUE
Monthly value times 12 over 365, for the days in the period.
LABOUR COST
Attendance time times the hourly rate of the person.
FAULT COSTS
Costs entered on faults at the contract sites.
MATERIALS COSTS
Materials used on tasks at the contract sites, at the price on the day of use.
MARGIN
Revenue minus labour, faults and materials, also as a percentage.

02Tasks step by step

  1. STEP 1Open Reports and go to the Rates tab.
  2. STEP 2For each person enter the net hourly rate and the date from which it applies.
  3. STEP 3Go to the Costs and profitability tab and set the period.
  4. STEP 4Check the contract margins and make sure there are no hours without a rate.

03What it connects to

CLIENTS, CONTRACTS AND LOCATIONS

Contracts

The monthly value and sites of a contract come from the Contracts screen.

Go to the topicContracts